High-bay warehouse Bürs
Build time: 5 weeks in 2001
Height: 17,00 m
Slipform area: 7.670 m²
Concrete poured: 965 m³
Slipforming speed: 3,40 m/day
Country: Austria
Client: Rinderer Bau
High-bay warehouse in Gaissau
Build time: 4,5 weeks in 2001
Height: 21,00 m
Slipform area: 7.741 m²
Concrete poured: 1.160 m³
Slipforming speed: 4,40 m/day
Country: Austria
Client: Loser Bau GesmbH & Co KG
High-bay warehouse for BMW München
Build time: October to December in 2016
Height: 29,51 m
Slipform area: 15.900 m²
Concrete poured: 2.243 m³
Slipforming speed: 4,00 m/day
Country: Germany
Client: Dipl.-Ing. Emil Hönninger GmbH & Co. Bauunternehmung KG
High-bay warehouse/Fire protection wall for Weinmann & Schanz GmbH
Build time: August to October in 2016
Height: 16,00 m
Slipform area: 10.330 m²
Concrete poured: 1.710 m³
Slipforming speed: 4,00 m/day
Country: Germany
Client: Stump GmbH
Bitschnau Gleit & Schalungstechnik GmbH
Gewerbestraße 8
A-6710 Nenzing
+43 (0)5525 64 778-0
+43 (0)5525 64 778-30
firma@bitschnau.com
We are looking for:
CONSTRUCTION FOREMEN
SKILLED WORKERS
BUILDING WORKERS
Please apply by phone to Günter Bitschnau on 05525/64778-0